Process Route
EAF
Timeline
Operating since 1972
Emissions
2025
0.29 Mt CO₂e
0.27 t CO₂e per tonne of steel
Typical EAF route: 0.5–0.7 t/t
Modelled estimate (Climate TRACE), not reported data. Methodology
Capacity (ttpa)
Crude Steel
2,000
EAF
2,000
Steel Units
EAF
unknown EAF (1)operating
Inputs & Energy
Power natural gas
Steel Products
wire rod, rebar, sections, mesh, bar, channel, angle
Ownership
Owner PT The Master Steel MFG
Parent PT The Master Steel MFG [100.0%]
Workforce 2,000 employees
Country Context
Indonesia crude steel production (USGS). Plant line shows nominal capacity, not output.
Explore
Location
Cakung
Asia Pacific
Indonesia