Process Route
BFBOF
Timeline
Construction1979
Idled1994
Capacity (ttpa)
Crude Steel
1,300
BOF
1,300
Blast Furnace
1,355
Sinter
2,610
Coking
880
Iron Units
BF
unknown BF (1)construction
Steel Units
Inputs & Energy
Power Captive Power Plant (110 mw)
Iron ore Itakpe Iron Ore Mine
Steel Products
rebar, sections, square, rod, billet, channel, angle, beam
Ownership
Owner Ajaokuta Steel Co Ltd
Parent Ajaokuta Steel Co Ltd [100.0%]
Workforce 10,000 employees
State ownership Full
Explore
Location
Ajaokuta
Africa
Nigeria
7.5113°, 6.6894°