Process Route
EAF
Timeline
Announced2005
Construction2007
Operating2010
Emissions
2025
0.16 Mt CO₂e
0.08 t CO₂e per tonne of steel
Typical EAF route: 0.5–0.7 t/t
Modelled estimate (Climate TRACE), not reported data. Methodology
Capacity (ttpa)
Crude Steel
2,600
EAF
2,600
Production
Crude steelproduction, GEM-compiled (Global Iron & Steel Tracker). Dashed line shows nominal capacity.
Steel Units
EAF
unknown EAF (1)operating
Inputs & Energy
Power 15.1 MW solar power plant (began in 2021-02)
Steel Products
pipe, coil, sheet
Ownership
Owner Tokyo Steel Manufacturing Co Ltd
Parent Tokyo Steel Manufacturing Co Ltd [100.0%]
Workforce 257 employees
Country Context
Japan crude steel production (USGS). Plant line shows nominal capacity, not output.
Explore
Location
Tahara
Asia Pacific
Japan
34.7020°, 137.2491°