Process Route
Timeline
Operating since 1996
Emissions
2025
2.04 Mt CO₂e
2.20 t CO₂e per tonne of steel
Typical BF-BOF route: 1.8–2.0 t/t
Modelled estimate (Climate TRACE), not reported data. Methodology
Capacity (ttpa)
Crude Steel
1,200
EAF
1,200
Blast Furnace
1,000
DRI
270
Sinter
2,800
Coking
1,100
Pelletising
3,000
Production
Crude steelproduction, GEM-compiled (Global Iron & Steel Tracker). Dashed line shows nominal capacity.
Iron Units
Steel Units
Inputs & Energy
Power Five captive power plants, combined capacity of 60MW
Iron ore Jayaswal Neco Metabodeli Mine (P100000128998), Jayaswal Neco Chhotedongar Mine (P100000129000), Dhobitola & Manegaon mine
Met coal Indian and imported
Steel Products
bar, bloom, billet, pig iron, rolled, DRI
Ownership
Owner Jayaswal Neco Industries Ltd
Parent Jayaswal Neco Industries Ltd [100.0%]
Workforce 9,503 employees
Country Context
India crude steel production (USGS). Plant line shows nominal capacity, not output.
Explore
Location
Raipur
Asia Pacific
India
21.3545°, 81.6764°