Jianglong Acheng Iron and Steel Co Ltd
operatingHarbin, Asia Pacific, China
ISO 14001ISO 50001
GEM wikiProcess Route
BFBOF
Timeline
Operating since 2001
Emissions
2025
2.60 Mt CO₂e
1.90 t CO₂e per tonne of steel
Typical BF-BOF route: 1.8–2.0 t/t
Modelled estimate (Climate TRACE), not reported data. Methodology
Capacity (ttpa)
Crude Steel
1,600
BOF
1,600
Blast Furnace
1,400
Iron Units
BF
unknown BF (1)operating
Steel Units
BOF
unknown BOF (1)operating
1,600 ttpawiki
Steel Products
coated, hot rolled
Ownership
Owner Jianglong Acheng Iron & Steel Co Ltd
Parent Beijing Jianlong Investment Co Ltd [87.6%]; unknown [12.4%]
Workforce 2,240 employees
Country Context
China crude steel production (USGS). Plant line shows nominal capacity, not output.
Explore
Location
Harbin
Asia Pacific
China
45.5620°, 126.9681°