Unitex Steel Mills Feni

construction

EAF route · Muhuriganj, Asia Pacific, Bangladesh

GEM wiki

Unitex Steel Mills Feni is a scrap-based steel plant: an electric arc furnace melts recycled steel scrap into new crude steel. The liquid steel is solidified into semi-finished shapes by continuous casting. The plant has a crude steel capacity of about 1.0 million tonnes per year. Its main products are rebar, rounds, angle, channel, billet, wire rod, beam.

Simulator · Beta

Operate a continuous caster

A free interactive model of the process — run a four-ladle sequence and see what breaks.

Launch the simulator →

Process Route

EAF

Timeline

Announced2020
Construction2023
Operating2026

Capacity (ttpa)

Crude Steel

1,000

EAF

1,000

Steel Units

EAF
unknown EAF (1)construction
1,000 ttpa100 tDanieliwiki

Inputs & Energy

Power Korerhat 400/230/132/33 kV Substation of PGCB

Steel Products

rebar, rounds, angle, channel, billet, wire rod, beam

Ownership

Owner Unitex Steel Mills Ltd

Parent Unitex Steel Mills Ltd [100.0%]

Workforce 516 employees

Learn the processes this plant uses

Nearby Plants

Explore