Metalloinvest OEMK
operatingOskol'skiy Elektrometallurgicheskiy Kombinat Imeni Alekseya Alekseyevicha Ugarova JSC · DRI–EAF route · Stary Oskol, Eurasia, Russia
Metalloinvest OEMK follows the DRI–EAF route: iron ore is reduced in the solid state to direct reduced iron by direct reduction, then melted into steel in an electric arc furnace. The liquid steel is solidified into semi-finished shapes by continuous casting. The plant has a crude steel capacity of about 3.5 million tonnes per year. Its main products are pipe, billet, dri.
Process Route
Timeline
Operating since 1984
Emissions
2025
2.39 Mt CO₂e
1.00 t CO₂e per tonne of steel
Modelled estimate (Climate TRACE), not reported data. Methodology
Capacity (ttpa)
Crude Steel
3,500
EAF
3,500
DRI
3,180
Pelletising
4,500
Production
Crude steelproduction, GEM-compiled (Global Iron & Steel Tracker). Dashed line shows nominal capacity.
Iron Units
Steel Units
Inputs & Energy
Iron ore Metalloinvest Mikhailovsky Mine (P100000128817); Metalloinvest Lebedinsky Mine (P100000128790)
Steel Products
pipe, billet, DRI
Ownership
Owner Oskol'skiy Elektrometallurgicheskiy Kombinat Imeni Alekseya Alekseyevicha Ugarova JSC
Parent YueSeM Holding Company LLC
Workforce 9,099 employees
Country Context
Russia crude steel production (USGS). Plant line shows nominal capacity, not output.
Learn the processes this plant uses
Nearby Plants
Other YueSeM Holding Company LLC plants
Explore
Location
Stary Oskol
Eurasia
Russia
51.1427°, 37.9405°
At a Glance
- Route
- DRI–EAF
- Crude steel capacity
- 3,500 ttpa
- Commissioned
- 1984
- Products
- Crude, semi-finished, finished rolled
- Certifications
- 2 recorded